Abram Street Rebuild Website Informs Drivers About Lane Closures, Construction Progress
By Office of Communication
Posted on March 23, 2018, March 23, 2018

Traffic-Alert

Below are the planned lane closures for the $26 million Abram Street Rebuild through Downtown Arlington.

To stay up-to-date on this transformative, two-year construction project between Cooper Street and Collins Street, visit the new Abram Street Rebuild webpage, www.ArlingtonTX.gov/Abram.

New or updated items will be indicated in bold.

Weekly Lane Closure Look Ahead

Closures are subject to changes due to weather and schedule. Below are anticipated traffic impacts for the coming weeks.

Abram Street between Pecan and Center:

The outside lanes of eastbound and westbound Abram Street between Pecan and Center streets, which is the area between City Hall and the Levitt Pavilion, will be closed to traffic through August 2018.

  • Temporary fencing has been installed along the north side of Founders Plaza across from City Hall to protect visitors to the Downtown park and the Levitt Pavilion from construction activities. Pedestrians can enter the park from the east side of Center Street or from the southwest corner of the Pecan and Abram streets intersection.

Abram Street between Weeks Avenue and Jeffries Street

  • Starting the week of March 25, the eastbound lanes of Abram Street will be closed between Weeks Avenue and Jeffries Street for the installation of sanitary sewer lines. However, two-way traffic will be maintained at all times during construction, which is set to last through June. This section is west of Collins Street.

Cooper and Abram streets intersection

  • Some turn lanes closures are expected for the Cooper and Abram streets intersection starting the week of March 25. Drivers will still be able to make turns, but the existing turn lanes from northbound Cooper Street onto eastbound Abram Street and from eastbound Abram Street onto southbound Cooper Street will be closed. Other work includes the removal of the traffic island at the southeast corner of the intersection and the relocation of the traffic signs. Work on this section is expected to last through May.

The City of Arlington has partnered with Waze to give drivers the best experience possible to get around town. Drivers can download Waze for free at www.waze.com/get for iOS and Android and see real-time traffic, find optimal routes, avoid road closures and more.

Abram Street, Put Technology to Work, Street Construction Projects